Name of internal auditInternal audit typeStatusCompletion date
PeopleSoftInformation Systems, HR ManagementCompletedQ2 2012−2013
Corporate Accountability and Administrative Renewal (CAAR) / Internal Control over Financial Reporting (ICFR)Financial ManagementCompletedQ4 2012–2013
Grants and Contributions ProcessFinancial ManagementCompletedQ4 2012–2013
HR Management – Work Force Adjustment Review – Phase 1HR ManagementCompletedQ3 2012–2013
Support to the Implementation of the Deficit Reduction Action PlanFinancial ManagementIn progressQ1 2013–2014
Capital Asset Maintenance and Renewal (incl. Assets Life Cycle Management)Asset ManagementIn progressQ3 2013–2014
IT Service DeliveryInformation SystemsIn progressQ2 2013–2014
Consultations with Various StakeholdersManagement ControlsIn progressQ3 2013–2014
Management of LaboratoriesManagement ControlsIn progressQ3 2013–2014
HR Management – Work Force Adjustment Review – Phase 2HR ManagementIn progressQ3 2013–2014
Fraud Risk Management ReviewFinancial ControlsIn progressQ1 2014–2015

All approved 2012-2013 audit reports can be found here.

Top of Section


Evaluations Table

Evaluations (current reporting period)
Name of evaluationProgramStatusCompletion date
Evaluation of the Transportation Sector EmissionsTransportation Sector Emissions (3.2.1.2)CompletedQ3 2012–2013
Evaluation of Federal Species at RiskSpecies at Risk (1.1.2)CompletedQ1 2012–2013
Evaluation of the Biodiversity Policy and PrioritiesBiodiversity Policy and Priorities (1.1.1)CompletedQ3 2012–2013
Evaluation of Health of the Oceans InitiativeProtected Areas (1.1.4.3)CompletedQ1 2012–2013
Evaluation of the Multilateral Fund of the Montreal ProtocolInternational Climate Change and Clean Air Partnerships (3.2.2)CompletedQ3 2012–2013
Contribution for Canada’s share of the Commission for Environmental Cooperation BudgetInternational Climate Change and Clean Air Partnerships (3.2.2)CompletedQ3 2012–2013
Evaluation of the Contaminated Sites ProgramContaminated Sites (3.1.4)In progressQ2 2013–2014
Evaluation of Eeyou Land ClaimMigratory Birds (1.1.3)In progressQ2 2013–2014
Evaluation of Advancing Conservation Interests in the Northwest Territories - ImplementationProtected Areas (1.1.4.3)In progressQ1 2013–2014
Evaluation of the Protected Areas ProgramProtected Areas (1.1.4.3)In progressQ2 2013–2014
Evaluation of the EcoAction Community Funding ProgramEcoAction Community Funding (1.3.3.1)In progressQ2 2013–2014
Evaluation of the Hydrological Service and Water Survey ProgramHydrological Service and Water Survey (1.2.3)In progressQ2 2013–2014
Evaluation of the Environmental Youth Employment ProgramEnvironmental Youth Employment (1.3.3.3)In progressQ3 2013–2014
Evaluation of the Community Ecosystem Partnerships ProgramCommunity Ecosystem Partnerships (1.3.4.5)In progressQ4 2013–2014
Evaluation of the Environmental Technology ProgramEnvironmental Technology Innovation (3.2.3.2)In progressQ4 2013–2014
Meteorological Areas Initiative (METAREAS)Meteorological and Ice Services in Support of Marine Navigation (2.2.2)In progressQ4 2013–2014
Federal Interlocutor’s Contribution Program and Effective Management of Métis Aboriginal RightsMigratory Birds (1.1.3)In progressQ2 2013–2014

All approved 2012–2013 evaluation reports that were led by Environment Canada (EC) can be found here.

Page 9
Date modified: